Array ( [id] => 395020 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 台江路风情桥启动主体结构吊装 力争明年春节前建成开放 [editor] => (编辑)叶虹 [has_thumb] => 1 [created] => 2024-11-22 10:01:07 [createdby] => 10025 [createdip] => 112.54.37.33 [published] => 2024-11-22 10:01:07 [publishedby] => 10025 [modified] => 2024-11-22 10:06:43 [modifiedby] => 10025 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 619 [virtual_pv] => 476 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => [cdv_type] => 0 [content] =>

台江路风情桥启动主体结构吊装

力争明年春节前建成开放,实现“闽江之心”与中亭街商业区一桥通达


图源:福州市城乡建总

“到位,到位!”“放!”20日凌晨5时,一场路灯下的攻坚行动加速展开。随着台江路上两段钢箱梁稳稳就位,标志着闽江北岸全线贯通风情桥完成首次钢箱梁吊装,进入主体施工的新阶段。

记者从福州城投集团所属市城乡建总获悉,作为闽江北岸全线贯通提升改造工程的组成部分,同时也是“闽江之心”的重要景观节点,风情桥施工已按下快进键。按计划,明年春节前,风情桥有望建成开放。

市城乡建总该项目负责人李翔介绍,风情桥位于台江路主干道(八一七路口至五一路口之间),北接中亭街利生苑,南邻城投大厦,横跨台江路。本次首吊的钢箱梁为桥面,长51.3米、宽4.5米。

“为了把对附近交通的影响降到最低,根据交警部门安排,每天0时至6时,台江路临时封闭,我们在这个时段集中作业,通过2部吊车配合,加快钢箱梁的吊装施工。”李翔说。

首吊完成,也让桥梁主体施工开足马力。21日凌晨,北侧楼梯的吊装工作也顺利完成。接下来,中间连廊、南侧楼梯及钟楼的吊装工作将陆续展开。

作为对沿江道路过街立体交通的补充完善,“跨越”台江路的风情桥,将打通台江路沿线的慢行“断点”,实现“闽江之心”与中亭街商业区一桥通达,形成更完善的“闽江之心”交通流线。

效果图 图源:福州市城乡建总

按设计方案,风情桥主桥会在北侧接入利生苑二楼商铺,并设置一对自动扶梯;在南侧城投大厦前,也将增设梯道与一对自动扶梯,最大程度满足市民游客的过街需求。今后,在这个完整的漫步空间内,沿线景观节点与商业资源将加速盘活,为“两江四岸”再添亮眼新景。

来源:福州日报

编辑:叶虹

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202411\/c903c08fc4b60da308842cf03ea6d016.jpeg","id":"2900336"}] [url] => /p/395020.html [all_pv] => 619 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( ) [article_thumb] => https://www.zohi.tv/a/10001/202411/c903c08fc4b60da308842cf03ea6d016.jpeg ) 1

台江路风情桥启动主体结构吊装 力争明年春节前建成开放

2024-11-22 10:01   福视悦动  

台江路风情桥启动主体结构吊装

力争明年春节前建成开放,实现“闽江之心”与中亭街商业区一桥通达


图源:福州市城乡建总

“到位,到位!”“放!”20日凌晨5时,一场路灯下的攻坚行动加速展开。随着台江路上两段钢箱梁稳稳就位,标志着闽江北岸全线贯通风情桥完成首次钢箱梁吊装,进入主体施工的新阶段。

记者从福州城投集团所属市城乡建总获悉,作为闽江北岸全线贯通提升改造工程的组成部分,同时也是“闽江之心”的重要景观节点,风情桥施工已按下快进键。按计划,明年春节前,风情桥有望建成开放。

市城乡建总该项目负责人李翔介绍,风情桥位于台江路主干道(八一七路口至五一路口之间),北接中亭街利生苑,南邻城投大厦,横跨台江路。本次首吊的钢箱梁为桥面,长51.3米、宽4.5米。

“为了把对附近交通的影响降到最低,根据交警部门安排,每天0时至6时,台江路临时封闭,我们在这个时段集中作业,通过2部吊车配合,加快钢箱梁的吊装施工。”李翔说。

首吊完成,也让桥梁主体施工开足马力。21日凌晨,北侧楼梯的吊装工作也顺利完成。接下来,中间连廊、南侧楼梯及钟楼的吊装工作将陆续展开。

作为对沿江道路过街立体交通的补充完善,“跨越”台江路的风情桥,将打通台江路沿线的慢行“断点”,实现“闽江之心”与中亭街商业区一桥通达,形成更完善的“闽江之心”交通流线。

效果图 图源:福州市城乡建总

按设计方案,风情桥主桥会在北侧接入利生苑二楼商铺,并设置一对自动扶梯;在南侧城投大厦前,也将增设梯道与一对自动扶梯,最大程度满足市民游客的过街需求。今后,在这个完整的漫步空间内,沿线景观节点与商业资源将加速盘活,为“两江四岸”再添亮眼新景。

来源:福州日报

编辑:叶虹