Array ( [id] => 381648 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 尤溪洲南立交改造工程桥梁主体结构即将完工 [editor] => (编辑)黄国伟 [has_thumb] => 1 [created] => 2024-03-08 09:02:56 [createdby] => 10270 [createdip] => 112.54.37.33 [published] => 2024-03-08 09:02:59 [publishedby] => 10270 [modified] => 2024-03-08 09:04:31 [modifiedby] => 10054 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 687 [virtual_pv] => 452 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => 018e1b812ba7c0010000ef24585d4d3f [cdv_type] => 1 [content] =>

尤溪洲南立交改造主线桥主体结构即将完工。记者 陈暖 摄

空中,匝道桥桥面护栏焊接全面展开;地上,辅路精细化品质提升细之又细,新建人行天桥施工每日不停……眼下,城区重要缓堵项目尤溪洲南立交改造工程已进入攻坚冲刺阶段。记者7日获悉,项目所有桥梁主体结构施工即将完成,提前完成一季度攻坚目标。

7日上午,记者来到该项目匝道桥建设现场。福州城投集团所属市城乡建总该项目相关负责人告诉记者,眼下,匝道桥的最后一联钢箱梁正加快吊装。

据了解,3座新建匝道桥是尤溪洲南立交改造工程的治堵核心,分别为长1116米的南二环往闽江大道方向匝道、长955米的闽江大道往南二环方向匝道和长235米的浦上大道左转闽江大道方向匝道。如今,3座桥梁已在空中挺立,层层交错。

“按照一季度的攻坚目标,桥梁得完成最后5联钢箱梁吊装,通过全面加大人机物料的投入,我们已顺利完成了4联吊装。”该负责人说,这几天,最后一联钢箱梁就是他们要“啃”下的主要目标。

与此同时,桥面系施工也在同步展开。“桥面的钢护栏焊接,正在多点作业。”项目施工单位中铁十七局相关工作人员介绍,现在已有3个班组“两班倒”高效作业。待护栏焊接完成后,混凝土浇捣、沥青铺装等桥面施工也将紧随其后。此外,闽江大道下穿通道上盖部分也已完成交通标线的施划,正在开展红绿灯等交通安全设施的安装。

考虑到通车后的交通组织,闽江大道上还将新添一座过街天桥,取代现有的下穿通道,让行人和非机动车安全通行。目前,新天桥的墩台浇筑和主墩焊接施工已完成,预计年内可建成开放。


来源:福州日报
编辑:黄国伟 责编:庄颖

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202403\/9a07952d494ac784496161fc92bafa13.jpeg","id":"2815101"}] [url] => /p/381648.html [all_pv] => 687 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 匝道 [1] => 闽江 [2] => 大道 [3] => 桥面 [4] => 尤溪 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( ) [article_thumb] => https://www.zohi.tv/a/10001/202403/9a07952d494ac784496161fc92bafa13.jpeg ) 1

尤溪洲南立交改造工程桥梁主体结构即将完工

2024-03-08 09:02   福视悦动  

尤溪洲南立交改造主线桥主体结构即将完工。记者 陈暖 摄

空中,匝道桥桥面护栏焊接全面展开;地上,辅路精细化品质提升细之又细,新建人行天桥施工每日不停……眼下,城区重要缓堵项目尤溪洲南立交改造工程已进入攻坚冲刺阶段。记者7日获悉,项目所有桥梁主体结构施工即将完成,提前完成一季度攻坚目标。

7日上午,记者来到该项目匝道桥建设现场。福州城投集团所属市城乡建总该项目相关负责人告诉记者,眼下,匝道桥的最后一联钢箱梁正加快吊装。

据了解,3座新建匝道桥是尤溪洲南立交改造工程的治堵核心,分别为长1116米的南二环往闽江大道方向匝道、长955米的闽江大道往南二环方向匝道和长235米的浦上大道左转闽江大道方向匝道。如今,3座桥梁已在空中挺立,层层交错。

“按照一季度的攻坚目标,桥梁得完成最后5联钢箱梁吊装,通过全面加大人机物料的投入,我们已顺利完成了4联吊装。”该负责人说,这几天,最后一联钢箱梁就是他们要“啃”下的主要目标。

与此同时,桥面系施工也在同步展开。“桥面的钢护栏焊接,正在多点作业。”项目施工单位中铁十七局相关工作人员介绍,现在已有3个班组“两班倒”高效作业。待护栏焊接完成后,混凝土浇捣、沥青铺装等桥面施工也将紧随其后。此外,闽江大道下穿通道上盖部分也已完成交通标线的施划,正在开展红绿灯等交通安全设施的安装。

考虑到通车后的交通组织,闽江大道上还将新添一座过街天桥,取代现有的下穿通道,让行人和非机动车安全通行。目前,新天桥的墩台浇筑和主墩焊接施工已完成,预计年内可建成开放。


来源:福州日报
编辑:黄国伟 责编:庄颖