Array ( [id] => 376539 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州地铁春节不停工不停产 [editor] => (编辑)林昱星 [has_thumb] => 1 [created] => 2024-02-07 10:04:45 [createdby] => 10006 [createdip] => 112.54.37.33 [published] => 2024-02-07 11:06:50 [publishedby] => 10006 [modified] => 2024-02-07 12:28:58 [modifiedby] => 10092 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 1534 [virtual_pv] => 440 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => 018d813bd906c0010000522a0f9f32b0 [cdv_type] => 1 [content] =>

福州地铁春节不停工不停产

1412名建设者和4505名运营人员坚守岗位

滨海快线东门站盾构施工现场。

今年春节假期,福州地铁在建线路不停工,17个工点1412名建设者将坚守施工一线。同时,福州地铁全线网4505名运营人员在岗在位,全力保障春节期间良好的运营秩序,方便群众有序出行。

日前,记者在滨海快线东门站看到,现场一派繁忙的施工景象,地面与地下三层的工人分工有序。东门站作为福州火车站站至东门站区间左右线盾构施工场地,仅左线区域实施围挡,实则地下双线盾构同时掘进施工。地面上龙门吊将盾构管片从左线洞口处吊入深28米的基坑,再由工人用电瓶车转运至右线。

“尽管多了地下转运工序,路面龙门吊也增加至3台,但这样可以压缩一半作业面,尽可能减少施工围挡,保证六一路正常通行。”业主代表王正说。

今年春节期间,滨海快线盾构左右线均正常掘进,施工单位中铁上海局管理人员42人与施工工人110人均在岗,进行两班倒掘进施工。在地下一层的滨海快线盾构监控中心安排多名管理人员24小时值班值守,监控盾构掘进各项参数,确保安全生产。

项目经理毕延哲是黑龙江人,已第三年在工地过年,今年他把家人接来福州团聚。除夕当晚,值守的人员会分批吃顿年夜饭,和家人视频拜年,再投入忙碌的施工中。

据介绍,福州地铁在建线路中,滨海快线15个站主体结构封顶,8座高架桥梁已完成主体结构施工,14个盾构区间双线贯通;4号线后通段盾构区间已完成93.33%,剩余洪金区间右线1台盾构正在掘进;6号线东调段5个车站已完成主体结构封顶,1个区间已贯通;2号线东延线4个车站主体结构封顶,4个车站正在进行围护结构施工,1个区间双线贯通。


来源:福州晚报
编辑:林昱星 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202402\/bb2dc68939d9d4d46587ac7bd7656fa3.jpeg","id":"2794707"}] [url] => /p/376539.html [all_pv] => 1534 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 盾构 [1] => 施工 [2] => 快线 [3] => 福州 [4] => 掘进 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( ) [article_thumb] => https://www.zohi.tv/a/10001/202402/bb2dc68939d9d4d46587ac7bd7656fa3.jpeg ) 1

福州地铁春节不停工不停产

2024-02-07 11:06   福视悦动  

福州地铁春节不停工不停产

1412名建设者和4505名运营人员坚守岗位

滨海快线东门站盾构施工现场。

今年春节假期,福州地铁在建线路不停工,17个工点1412名建设者将坚守施工一线。同时,福州地铁全线网4505名运营人员在岗在位,全力保障春节期间良好的运营秩序,方便群众有序出行。

日前,记者在滨海快线东门站看到,现场一派繁忙的施工景象,地面与地下三层的工人分工有序。东门站作为福州火车站站至东门站区间左右线盾构施工场地,仅左线区域实施围挡,实则地下双线盾构同时掘进施工。地面上龙门吊将盾构管片从左线洞口处吊入深28米的基坑,再由工人用电瓶车转运至右线。

“尽管多了地下转运工序,路面龙门吊也增加至3台,但这样可以压缩一半作业面,尽可能减少施工围挡,保证六一路正常通行。”业主代表王正说。

今年春节期间,滨海快线盾构左右线均正常掘进,施工单位中铁上海局管理人员42人与施工工人110人均在岗,进行两班倒掘进施工。在地下一层的滨海快线盾构监控中心安排多名管理人员24小时值班值守,监控盾构掘进各项参数,确保安全生产。

项目经理毕延哲是黑龙江人,已第三年在工地过年,今年他把家人接来福州团聚。除夕当晚,值守的人员会分批吃顿年夜饭,和家人视频拜年,再投入忙碌的施工中。

据介绍,福州地铁在建线路中,滨海快线15个站主体结构封顶,8座高架桥梁已完成主体结构施工,14个盾构区间双线贯通;4号线后通段盾构区间已完成93.33%,剩余洪金区间右线1台盾构正在掘进;6号线东调段5个车站已完成主体结构封顶,1个区间已贯通;2号线东延线4个车站主体结构封顶,4个车站正在进行围护结构施工,1个区间双线贯通。


来源:福州晚报
编辑:林昱星 责编:林真贞