Array ( [id] => 371931 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 长乐机场二期航站区高架桥开始架梁 [editor] => (编辑)黄国伟 [has_thumb] => 1 [created] => 2024-01-14 10:51:15 [createdby] => 10270 [createdip] => 112.54.37.33 [published] => 2024-01-14 11:50:00 [publishedby] => 10270 [modified] => 2024-01-14 11:50:12 [modifiedby] => 10054 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 669 [virtual_pv] => 447 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => 018d05ce7ba4c00100001f54e99f5b5d [cdv_type] => 1 [content] =>

施工现场 。(项目部供图)

11日,长乐国际机场二期扩建航站区工程高架桥进入箱梁施工阶段。施工人员连续奋战近12小时,完成了首联浇筑,为后续大规模现浇箱梁施工积累宝贵经验。

该高架桥长约2910米,含有9条匝道,本次浇筑的为F1联箱梁,长52米,标准宽度10米,距离地面高度5米至8.5米。

据悉,高架桥明年5月将具备交付条件,将助力福州机场加速跨入“双跑道、双航站楼”时代。


来源:福州日报
编辑:黄国伟 责编:庄颖

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202401\/ad88810cc4e30280aa7933aeccf560c7.jpeg","id":"2778834"}] [url] => /p/371931.html [all_pv] => 669 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 箱梁 [1] => 高架桥 [2] => 浇筑 [3] => 施工 [4] => 机场 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( ) [article_thumb] => https://www.zohi.tv/a/10001/202401/ad88810cc4e30280aa7933aeccf560c7.jpeg ) 1

长乐机场二期航站区高架桥开始架梁

2024-01-14 11:50   福视悦动  

施工现场 。(项目部供图)

11日,长乐国际机场二期扩建航站区工程高架桥进入箱梁施工阶段。施工人员连续奋战近12小时,完成了首联浇筑,为后续大规模现浇箱梁施工积累宝贵经验。

该高架桥长约2910米,含有9条匝道,本次浇筑的为F1联箱梁,长52米,标准宽度10米,距离地面高度5米至8.5米。

据悉,高架桥明年5月将具备交付条件,将助力福州机场加速跨入“双跑道、双航站楼”时代。


来源:福州日报
编辑:黄国伟 责编:庄颖