Array ( [id] => 353877 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 直通马尾!福州这条地铁重大进展! [editor] => (编辑)黄国伟 [has_thumb] => 1 [created] => 2023-10-09 15:04:18 [createdby] => 10270 [createdip] => 112.54.37.33 [published] => 2023-10-09 15:04:20 [publishedby] => 10270 [modified] => 2023-10-09 15:08:30 [modifiedby] => 10054 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 1389 [virtual_pv] => 395 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => 018b13300793c001000078afce03e4b0 [cdv_type] => 1 [content] =>

刚刚,福州地铁2号线东延线“福马号”盾构机在洋里—魁岐区间中间风井顺利始发,这标志着2号线东延线工程建设,取得了关键性进展,为后续盾构掘进施工提供了有利条件。

 

2号线东延线洋里至魁岐盾构区间全长约3110米。

区间自中间风井始发向北沿鼓山隧道方向敷设,其间下穿魁岐互通高架桥、鼓山隧道西洞口人行天桥,上跨鼓山补水隧道等重要风险源。盾构机在上软下硬复合地层中近距离下穿福马路箱涵,最后抵达洋里站接收,盾构施工过程中环境风险较高。


此外,本区间穿越的地质条件复杂,挖掘难度大,部分区间容易发生透水,盾构接收段范围还存在上软下硬地层,盾构施工难度大。

为了保障施工顺利开展,福州地铁最终选择了土压/TBM双模盾构的模式。此次在洋里—魁岐区间中间风井始发“福马号”盾构机是一台土压/TBM双模盾构机,整机重达510吨,设计最大推进速度达80毫米每分钟,具有开挖安全、掘进高效等显著优点。

福州地铁2号线东延线全长约14.6千米,共设9座车站,洋里站、魁岐站、葆桢路站、儒江站、下德站、马江渡站、船政文化城站、罗星塔站、青洲站,该线路是缓解福州主城区与马尾之间客流通行压力的交通走廊,建成后将极大加强马尾区与福州主城中心的联系。



东延线建设正在加速,截至目前2个车站主体结构已封顶,2个车站正在主体结构施工,4个车站正在围护结构施工;1个区间双线贯通,1个区间正在盾构掘进施工。

离2号线东延线建成通车的日子越来越近,以后,马尾与福州主城区的交通将更快更便利,小伙伴们,期待吗?


来源:福州晚报
编辑:黄国伟 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202310\/31747572205e91fb1674c91c412b6c66.jpeg","id":"2709375"},{"url":"\/a\/10001\/202310\/ed1ea71993a03c77fcacf22f868ad88b.jpeg","id":"2709378"},{"url":"\/a\/10001\/202310\/15feb4d657befe9e9320176af445a3e2.jpeg","id":"2709381"}] [url] => /p/353877.html [all_pv] => 1389 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 盾构 [1] => 东延线 [2] => 号线 [3] => 区间 [4] => 施工 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( ) [article_thumb] => https://www.zohi.tv/a/10001/202310/31747572205e91fb1674c91c412b6c66.jpeg ) 1

直通马尾!福州这条地铁重大进展!

2023-10-09 15:04   福视悦动  

刚刚,福州地铁2号线东延线“福马号”盾构机在洋里—魁岐区间中间风井顺利始发,这标志着2号线东延线工程建设,取得了关键性进展,为后续盾构掘进施工提供了有利条件。

 

2号线东延线洋里至魁岐盾构区间全长约3110米。

区间自中间风井始发向北沿鼓山隧道方向敷设,其间下穿魁岐互通高架桥、鼓山隧道西洞口人行天桥,上跨鼓山补水隧道等重要风险源。盾构机在上软下硬复合地层中近距离下穿福马路箱涵,最后抵达洋里站接收,盾构施工过程中环境风险较高。


此外,本区间穿越的地质条件复杂,挖掘难度大,部分区间容易发生透水,盾构接收段范围还存在上软下硬地层,盾构施工难度大。

为了保障施工顺利开展,福州地铁最终选择了土压/TBM双模盾构的模式。此次在洋里—魁岐区间中间风井始发“福马号”盾构机是一台土压/TBM双模盾构机,整机重达510吨,设计最大推进速度达80毫米每分钟,具有开挖安全、掘进高效等显著优点。

福州地铁2号线东延线全长约14.6千米,共设9座车站,洋里站、魁岐站、葆桢路站、儒江站、下德站、马江渡站、船政文化城站、罗星塔站、青洲站,该线路是缓解福州主城区与马尾之间客流通行压力的交通走廊,建成后将极大加强马尾区与福州主城中心的联系。



东延线建设正在加速,截至目前2个车站主体结构已封顶,2个车站正在主体结构施工,4个车站正在围护结构施工;1个区间双线贯通,1个区间正在盾构掘进施工。

离2号线东延线建成通车的日子越来越近,以后,马尾与福州主城区的交通将更快更便利,小伙伴们,期待吗?


来源:福州晚报
编辑:黄国伟 责编:林真贞