Array ( [id] => 335697 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 明年6月启用!福州火车南站进出迎来新变化 [editor] => (编辑)黄国伟 [has_thumb] => 1 [created] => 2023-06-29 18:12:42 [createdby] => 10270 [createdip] => 112.54.37.33 [published] => 2023-06-29 18:12:45 [publishedby] => 10270 [modified] => 2023-06-29 18:51:57 [modifiedby] => 10092 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 1627 [virtual_pv] => 372 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => 01890696bc4dc0010000c765d271c0ac [cdv_type] => 1 [content] =>

28日,记者从福州市城乡建设局获悉,备受市民关注的福州市火车南站东侧配套道路及景观绿化工程(一期)迎来新进展,9月底可具备进出站及停车功能,预计明年6月将正式启用。

施工建设中。

新建“三路、两桥、一排水”

该项目由福州城投集团所属市城乡建总建设,中建海峡基础设施总承包分公司施工。项目是福厦客专(在建)福州南站的配套市政道路,位于南站广场东侧,南起环岛路,北接福泉高速连接线。建设内容包含改造、新建3条道路,新建两座桥梁与一个排水系统。

建成效果图。中建海峡供图

北侧永南路将新建一座线交桥,形成“主路+桥面+辅路”的结构,新增两条进站匝道接入站房落客平台及二层停车楼。

南侧环岛路将拓宽原有6米村道,并完善道路功能,在道路两侧增设非机动车道和人行道。同时新建一座长490米钢箱梁桥和三条出入站匝道接入站房落客平台及二层停车楼,把双向6车道升级为双向8车道。

此外,永南路侧、环岛路侧新建1307米雨水管道与1597米污水管道,将路面积水排入胪雷河与污水干管,永久排水系统已基本成型,有效防止内涝。

搭乘福厦高铁可实现快速进站

目前,桥梁下部结构施工全面展开,已完成桩基、承台、灌注施工,7月上旬将转入上部施工。火车南站东站房永南路侧、环岛路侧完成雨水管网接驳,土石方工程已完成80%,桥梁及围护桩基已完成68%,进度正按序时推进。

建成效果图。中建海峡供图

据项目相关负责人介绍,9月底,项目可完成火车南站东站房地面出入口接驳及警备通道接驳,车辆可从永南路、环岛路辅路地面进出新站房一层落客平台,从站房内部进出二层停车场,可从环岛路辅路进出新站房警备通道,具备进出站及停车功能。

明年6月,项目可完成永南路、环岛路5条匝道桥建设,车辆可从匝道快速进入新站房二层停车场或一层落客平台。作为打通福泉快速路与环岛路的快速连接通道,项目建成后将衔接环岛路、永南路等城市快速路、城市主干路,届时搭乘福厦高铁的市民将实现快速进站,火车南站周边通行效率将大大优化提升,三江口片区路网将逐步完善,片区地块加快开发。


来源:福州新闻网
编辑:黄国伟 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202306\/cd7541f893784a56c262d08a2a477eea.jpeg","id":"2646567"}] [url] => /p/335697.html [all_pv] => 1627 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 环岛路 [1] => 站房 [2] => 南站 [3] => 南路 [4] => 落客 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( ) [article_thumb] => https://www.zohi.tv/a/10001/202306/cd7541f893784a56c262d08a2a477eea.jpeg ) 1

明年6月启用!福州火车南站进出迎来新变化

2023-06-29 18:12   福视悦动  

28日,记者从福州市城乡建设局获悉,备受市民关注的福州市火车南站东侧配套道路及景观绿化工程(一期)迎来新进展,9月底可具备进出站及停车功能,预计明年6月将正式启用。

施工建设中。

新建“三路、两桥、一排水”

该项目由福州城投集团所属市城乡建总建设,中建海峡基础设施总承包分公司施工。项目是福厦客专(在建)福州南站的配套市政道路,位于南站广场东侧,南起环岛路,北接福泉高速连接线。建设内容包含改造、新建3条道路,新建两座桥梁与一个排水系统。

建成效果图。中建海峡供图

北侧永南路将新建一座线交桥,形成“主路+桥面+辅路”的结构,新增两条进站匝道接入站房落客平台及二层停车楼。

南侧环岛路将拓宽原有6米村道,并完善道路功能,在道路两侧增设非机动车道和人行道。同时新建一座长490米钢箱梁桥和三条出入站匝道接入站房落客平台及二层停车楼,把双向6车道升级为双向8车道。

此外,永南路侧、环岛路侧新建1307米雨水管道与1597米污水管道,将路面积水排入胪雷河与污水干管,永久排水系统已基本成型,有效防止内涝。

搭乘福厦高铁可实现快速进站

目前,桥梁下部结构施工全面展开,已完成桩基、承台、灌注施工,7月上旬将转入上部施工。火车南站东站房永南路侧、环岛路侧完成雨水管网接驳,土石方工程已完成80%,桥梁及围护桩基已完成68%,进度正按序时推进。

建成效果图。中建海峡供图

据项目相关负责人介绍,9月底,项目可完成火车南站东站房地面出入口接驳及警备通道接驳,车辆可从永南路、环岛路辅路地面进出新站房一层落客平台,从站房内部进出二层停车场,可从环岛路辅路进出新站房警备通道,具备进出站及停车功能。

明年6月,项目可完成永南路、环岛路5条匝道桥建设,车辆可从匝道快速进入新站房二层停车场或一层落客平台。作为打通福泉快速路与环岛路的快速连接通道,项目建成后将衔接环岛路、永南路等城市快速路、城市主干路,届时搭乘福厦高铁的市民将实现快速进站,火车南站周边通行效率将大大优化提升,三江口片区路网将逐步完善,片区地块加快开发。