Array ( [id] => 330879 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 最新进展!滨海快线11座车站主体结构封顶 [editor] => (编辑)黄国伟 [has_thumb] => 1 [created] => 2023-05-29 14:46:54 [createdby] => 10270 [createdip] => 112.54.37.33 [published] => 2023-05-29 14:47:01 [publishedby] => 10270 [modified] => 2023-05-29 14:50:06 [modifiedby] => 10054 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 972 [virtual_pv] => 438 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => 018866360f79c001000003747acd85e5 [cdv_type] => 1 [content] =>

记者28日从市城乡建设局获悉,福州滨海快线15座车站中,已有11座完成主体结构封顶。线路盾构施工正加快推进,已完成全部盾构区间长度的近八成,全线桥梁预计今年完成主体结构施工。

滨海快线的15座车站中,机场站、大数据站、闽都站、南公园站、盖山站、帝封江站、祥谦站、首占站、莲花山站、滨海西站、文岭站等11座车站,已完成主体结构封顶,福州火车站站、东门站、三叉街站、滨海新城中央商务区站正进行主体结构施工。

滨海快线全线有19.89公里的桥梁,预计今年完成主体结构施工。另外,滨海快线全线共有17个盾构区间(隧道)工程,目前已实现5个区间单线贯通、8个区间双线贯通,累计完成施工57公里,占全部盾构区间长度的77%。

滨海快线共有8个高架区间,其中3个高架区间已架设完成,累计完成区间施工长度约14.6公里,占全部高架区间长度的73%。

滨海快线起于福州火车站站,终于文岭站,呈西北至东南走向,途经福州老城区、滨海新城、长乐国际机场,总长约62.4公里。未来,滨海快线将采用时速140公里的A型电客车,实现福州市中心至滨海新城30分钟内通达、福州火车站至长乐国际机场40分钟通达,并实现与多条规划地铁线路及福平铁路换乘,助力打造闽东北协同发展区中心城区1小时交通圈。


来源:福州晚报
编辑:黄国伟 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202305\/2d938e77073e0fe39f4becec7b7a583f.png","id":"2627694"}] [url] => /p/330879.html [all_pv] => 972 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 滨海 [1] => 快线 [2] => 区间 [3] => 施工 [4] => 完成 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( ) [article_thumb] => https://www.zohi.tv/a/10001/202305/2d938e77073e0fe39f4becec7b7a583f.png ) 1

最新进展!滨海快线11座车站主体结构封顶

2023-05-29 14:47   福视悦动  

记者28日从市城乡建设局获悉,福州滨海快线15座车站中,已有11座完成主体结构封顶。线路盾构施工正加快推进,已完成全部盾构区间长度的近八成,全线桥梁预计今年完成主体结构施工。

滨海快线的15座车站中,机场站、大数据站、闽都站、南公园站、盖山站、帝封江站、祥谦站、首占站、莲花山站、滨海西站、文岭站等11座车站,已完成主体结构封顶,福州火车站站、东门站、三叉街站、滨海新城中央商务区站正进行主体结构施工。

滨海快线全线有19.89公里的桥梁,预计今年完成主体结构施工。另外,滨海快线全线共有17个盾构区间(隧道)工程,目前已实现5个区间单线贯通、8个区间双线贯通,累计完成施工57公里,占全部盾构区间长度的77%。

滨海快线共有8个高架区间,其中3个高架区间已架设完成,累计完成区间施工长度约14.6公里,占全部高架区间长度的73%。

滨海快线起于福州火车站站,终于文岭站,呈西北至东南走向,途经福州老城区、滨海新城、长乐国际机场,总长约62.4公里。未来,滨海快线将采用时速140公里的A型电客车,实现福州市中心至滨海新城30分钟内通达、福州火车站至长乐国际机场40分钟通达,并实现与多条规划地铁线路及福平铁路换乘,助力打造闽东北协同发展区中心城区1小时交通圈。


来源:福州晚报
编辑:黄国伟 责编:林真贞