Array ( [id] => 252960 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州地铁多项目迎最新进展!涉及4、5、6号线…… [editor] => (编辑)黄国伟 [has_thumb] => 1 [created] => 2022-03-31 14:57:53 [createdby] => 10270 [createdip] => 112.54.37.33 [published] => 2022-03-31 14:57:57 [publishedby] => 10270 [modified] => 2022-03-31 18:24:18 [modifiedby] => 10092 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 1407 [virtual_pv] => 412 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => 017fdec37186c001000083c53c0dceb1 [cdv_type] => 1 [content] =>

好消息!

今年第一季度,福州地铁4号线、5号线、6号线……多个项目迎新进展!

4号线进展

29日,随着东街口站-省立医院站区间(以下简称东省区间)右线盾构最后一环管片拼装结束,4号线东省区间如期贯通,也为福州地铁第一季度“开门红”交上崭新的答卷。东省区间长约576米,盾构机自省立医院站始发,沿东街向西到达东街口站完成接收。

盾构抵达接收的钢套筒内

截至目前,4号线洞通进度已完成98%,除洪山桥至金牛山过江区间外的盾构区间已全部洞通。4号线半洲站-建新站、西门站-东街口站、东门站-省立医院站等4个区间双线贯通,城门站下穿1号线冷冻暗挖通道贯通,前锦车辆段主体结构完工。下阶段,福州地铁将组织已洞通区间铺轨,同时开展附属结构收尾作业。

滨海快线进展

3月23日,福州滨海快线大象山隧道盾构双线贯通。这是国内首条大直径单护盾TBM山岭隧道地铁项目,全长4.53公里,也是福州轨道交通目前遇到距离最长、硬度最高的山岭隧道。

除大象山隧道贯通外,滨海快线一季度还完成了岱岭隧道双线贯通、莲花山站主体结构封顶施工。目前,滨海快线全线8个站完成主体结构施工,13个盾构区间已始发18台盾构机,隧道已掘进30%。

TOD项目进展

地铁·睿达项目位于福州市晋安区华林路与茶园路交叉口东北角,紧邻福州地铁1号线斗门站B出口,为酒店、商业性质用地。自去年9月底开工以来,该项目抓紧推进施工进度,目前进入主体结构施工阶段,已完成地下室土方开挖、承台砌筑、底板垫层浇筑等作业。

其余项目如智慧园、2号线南门兜站地下空间开发工程等,目前正有序推进施工前期各项工作。其中,智慧园项目已完成现场围挡及场地平整,南门兜项目完成前期交通导改申请、管线迁改排查、绿化移植梳理等工作,均已完成一季度施工目标。

运营筹备进展

原浩 摄

这段时间,5号线首通段、6号线都在为开通开展各项运营筹备工作。目前两条线路均实现空载试运行。

陈鹤 摄

铆足“虎劲”和福州地铁一起加速前进吧!


来源:福州地铁微信公众号
编辑:黄国伟 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202203\/6f3f86b706465fc036c69f2fcf04ccf4.png","id":"2275155"},{"url":"\/a\/10001\/202203\/9b85819a17cb664b698996920f83b634.jpeg","id":"2275161"},{"url":"\/a\/10001\/202203\/5c0610c736bd7308b36d796d768bed4f.png","id":"2275164"}] [url] => /p/252960.html [all_pv] => 1407 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 号线 [1] => 盾构 [2] => 地铁 [3] => 福州 [4] => 贯通 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( ) [article_thumb] => https://www.zohi.tv/a/10001/202203/6f3f86b706465fc036c69f2fcf04ccf4.png ) 1

福州地铁多项目迎最新进展!涉及4、5、6号线……

2022-03-31 14:57   福视悦动  

好消息!

今年第一季度,福州地铁4号线、5号线、6号线……多个项目迎新进展!

4号线进展

29日,随着东街口站-省立医院站区间(以下简称东省区间)右线盾构最后一环管片拼装结束,4号线东省区间如期贯通,也为福州地铁第一季度“开门红”交上崭新的答卷。东省区间长约576米,盾构机自省立医院站始发,沿东街向西到达东街口站完成接收。

盾构抵达接收的钢套筒内

截至目前,4号线洞通进度已完成98%,除洪山桥至金牛山过江区间外的盾构区间已全部洞通。4号线半洲站-建新站、西门站-东街口站、东门站-省立医院站等4个区间双线贯通,城门站下穿1号线冷冻暗挖通道贯通,前锦车辆段主体结构完工。下阶段,福州地铁将组织已洞通区间铺轨,同时开展附属结构收尾作业。

滨海快线进展

3月23日,福州滨海快线大象山隧道盾构双线贯通。这是国内首条大直径单护盾TBM山岭隧道地铁项目,全长4.53公里,也是福州轨道交通目前遇到距离最长、硬度最高的山岭隧道。

除大象山隧道贯通外,滨海快线一季度还完成了岱岭隧道双线贯通、莲花山站主体结构封顶施工。目前,滨海快线全线8个站完成主体结构施工,13个盾构区间已始发18台盾构机,隧道已掘进30%。

TOD项目进展

地铁·睿达项目位于福州市晋安区华林路与茶园路交叉口东北角,紧邻福州地铁1号线斗门站B出口,为酒店、商业性质用地。自去年9月底开工以来,该项目抓紧推进施工进度,目前进入主体结构施工阶段,已完成地下室土方开挖、承台砌筑、底板垫层浇筑等作业。

其余项目如智慧园、2号线南门兜站地下空间开发工程等,目前正有序推进施工前期各项工作。其中,智慧园项目已完成现场围挡及场地平整,南门兜项目完成前期交通导改申请、管线迁改排查、绿化移植梳理等工作,均已完成一季度施工目标。

运营筹备进展

原浩 摄

这段时间,5号线首通段、6号线都在为开通开展各项运营筹备工作。目前两条线路均实现空载试运行。

陈鹤 摄

铆足“虎劲”和福州地铁一起加速前进吧!


来源:福州地铁微信公众号