Array ( [id] => 387443 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 福州地铁4条在建线路有序推进 滨海快线机中区间右线贯通 [editor] => (编辑)黄国伟 [has_thumb] => 1 [created] => 2024-05-04 16:37:23 [createdby] => 10270 [createdip] => 112.54.37.33 [published] => 2024-05-04 16:37:27 [publishedby] => 10270 [modified] => 2024-05-04 16:39:04 [modifiedby] => 10054 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 530 [virtual_pv] => 372 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => 018f42aa1443c00100000be05ced2320 [cdv_type] => 1 [content] =>

近日,滨海快线机场站至中间风井区间(简称“机中区间”)右线盾构机缓缓进入预设钢套筒,标志着机中区间右线实现隧道贯通。

据了解,机中区间长2.95公里,存在多段全断面硬岩、上软下硬及孤石群等不良地层,以及浅埋深、全断面粉细砂等频变地层,区间岩石强度最高达205.8MPa。同时机中区间复合地质条件下长距离下穿多处重大风险源,是滨海快线地质最复杂的盾构区间。

为提高盾构机与复杂地层的适应性,项目团队对盾构设备进行优化改造,实现复杂地层盾构施工提速增效。

在盾构机于复合地层下穿机场区域期间,项目团队依次启动机中区间4座联络通道建设,与盾构掘进同步实施,并在右线盾构贯通前夕完成全部联络通道施工,有效节约项目总体工期约3个月。多座联络通道与双线盾构掘进同步实施,这在行业内尚属首次。

记者从福州地铁集团了解到,“五一”假期,福州地铁建设者坚守施工一线,4条在建线路有序推进中,在建里程约86.95公里,建成后预计增加车站33座。

截至目前,滨海快线15个车站完成主体结构封顶,15个区间(隧道)双线贯通。

4号线后通段4个车站已全部封顶,区间仅剩洪金区间右线暂未洞通,风水电及装修累计完成94%,机电系统累计完成90%。

2号线东延线4个车站主体结构封顶(含代建),4个车站正进行围护结构施工或土方开挖,1个区间双线贯通(含代建),3个区间盾构正在掘进(含代建)。

6号线东调段5个车站主体均已结构封顶,1个区间双线贯通,2个区间盾构正在掘进。


来源:福州晚报
编辑:黄国伟 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202405\/df15fd9da580805580783d1a2168db88.jpeg","id":"2868713"}] [url] => /p/387443.html [all_pv] => 530 [pages] => 1 [author] => [terms] => Array ( [2] => Array ( [0] => 盾构 [1] => 区间 [2] => 车站 [3] => 机中 [4] => 贯通 ) [4] => Array ( [0] => 福视悦动 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( ) [article_thumb] => https://www.zohi.tv/a/10001/202405/df15fd9da580805580783d1a2168db88.jpeg ) 1

福州地铁4条在建线路有序推进 滨海快线机中区间右线贯通

2024-05-04 16:37   福视悦动  

近日,滨海快线机场站至中间风井区间(简称“机中区间”)右线盾构机缓缓进入预设钢套筒,标志着机中区间右线实现隧道贯通。

据了解,机中区间长2.95公里,存在多段全断面硬岩、上软下硬及孤石群等不良地层,以及浅埋深、全断面粉细砂等频变地层,区间岩石强度最高达205.8MPa。同时机中区间复合地质条件下长距离下穿多处重大风险源,是滨海快线地质最复杂的盾构区间。

为提高盾构机与复杂地层的适应性,项目团队对盾构设备进行优化改造,实现复杂地层盾构施工提速增效。

在盾构机于复合地层下穿机场区域期间,项目团队依次启动机中区间4座联络通道建设,与盾构掘进同步实施,并在右线盾构贯通前夕完成全部联络通道施工,有效节约项目总体工期约3个月。多座联络通道与双线盾构掘进同步实施,这在行业内尚属首次。

记者从福州地铁集团了解到,“五一”假期,福州地铁建设者坚守施工一线,4条在建线路有序推进中,在建里程约86.95公里,建成后预计增加车站33座。

截至目前,滨海快线15个车站完成主体结构封顶,15个区间(隧道)双线贯通。

4号线后通段4个车站已全部封顶,区间仅剩洪金区间右线暂未洞通,风水电及装修累计完成94%,机电系统累计完成90%。

2号线东延线4个车站主体结构封顶(含代建),4个车站正进行围护结构施工或土方开挖,1个区间双线贯通(含代建),3个区间盾构正在掘进(含代建)。

6号线东调段5个车站主体均已结构封顶,1个区间双线贯通,2个区间盾构正在掘进。


来源:福州晚报
编辑:黄国伟 责编:林真贞