Array ( [id] => 364806 [appid] => 1 [topicid] => 0 [galleryid] => 0 [channel_pc] => 1 [channel_wap] => 1 [channel_phone] => 1 [channel_pad] => 0 [title] => 速看!福州这条路,即将大变样! [editor] => (编辑)王蕾 [has_thumb] => 1 [created] => 2023-12-09 17:34:37 [createdby] => 10052 [createdip] => 112.54.37.33 [published] => 2023-12-09 17:34:37 [publishedby] => 10052 [modified] => 2023-12-09 17:35:19 [modifiedby] => 10054 [up_line_time] => 0 [down_line_time] => 0 [digg] => 0 [pv] => 1150 [virtual_pv] => 437 [virtual_digg] => 0 [click_pv] => 0 [comments] => 0 [shares] => 0 [recommend] => 0 [audit_step] => 0 [importance] => 0 [status] => 6 [enableaudit] => 1 [enablecopyright] => 0 [locktime] => 0 [locker] => 0 [sort] => 0 [watermark] => 0 [is_auto_published] => 0 [origin] => 0 [syscomments] => 0 [cdv_id] => [cdv_type] => 0 [content] =>

最新消息!福州市发改委批复!为缓解东二环、东三环交通压力,前横路快速化改造工程即将进行。

根据批复,项目位于晋安区、台江区,起于鳌峰路(起点接前横闽江大桥接线工程),向北延伸途经光明港、远洋路、前屿路、福马路、化工路、横屿路、鹤林路,终点与三环园中互通相接。

建设规模和内容

道路全长5285米,设计宽度40~70米。沿线在鳌峰路北侧设置两座上下匝道,远洋路、前屿路、化工路、鹤林路设置四座立交,沿线共有四座跨河桥梁(一座新建、三座拼宽)、新建一座人行天桥,改造两座人行地道(远洋及化工立交范围)。

项目估算总投资466773.90万元,建设工期为36个月,期待早日动工!


来源:福州市人民政府官网
编辑:王蕾 责编:林真贞

[subtitle] => [pagecount] => 1 [sourceurl] => [description] => [thumb] => [{"url":"\/a\/10001\/202312\/51037109d84859bc7f6d0254488fe9f3.jpeg","id":"2754819"}] [url] => /p/364806.html [all_pv] => 1150 [pages] => 1 [author] => [terms] => Array ( [4] => Array ( [0] => 福视悦动 ) [2] => Array ( [0] => 鳌峰 [1] => 远洋 [2] => 立交 [3] => 四座 [4] => 化工 ) ) [menu] => 226 [attachments] => Array ( ) [relates] => Array ( ) [article_thumb] => https://www.zohi.tv/a/10001/202312/51037109d84859bc7f6d0254488fe9f3.jpeg ) 1

速看!福州这条路,即将大变样!

2023-12-09 17:34   福视悦动  

最新消息!福州市发改委批复!为缓解东二环、东三环交通压力,前横路快速化改造工程即将进行。

根据批复,项目位于晋安区、台江区,起于鳌峰路(起点接前横闽江大桥接线工程),向北延伸途经光明港、远洋路、前屿路、福马路、化工路、横屿路、鹤林路,终点与三环园中互通相接。

建设规模和内容

道路全长5285米,设计宽度40~70米。沿线在鳌峰路北侧设置两座上下匝道,远洋路、前屿路、化工路、鹤林路设置四座立交,沿线共有四座跨河桥梁(一座新建、三座拼宽)、新建一座人行天桥,改造两座人行地道(远洋及化工立交范围)。

项目估算总投资466773.90万元,建设工期为36个月,期待早日动工!


来源:福州市人民政府官网
编辑:王蕾 责编:林真贞